Prince William County Department of Development Services issued changes to its building requirements for new data centers.
Data center design plans will be required to include all areas of new structures to meet the VUSBC minimum requirements for occupancy. Areas in the building not designated for immediate use shall require design plans for either Storage (S-1) Use Group or Business (B) Use Group, to meet the VUSBC minimum requirements.
A data center will be permitted as one building, resulting in one certificate of occupancy. After the certificate of occupancy is issued, an alteration/repair building permit will be issued to allow S-1 and B use group areas to be converted or fit-out.
If S-1 or B use groups need to be converted or fit-out during the initial construction, a design plan revision must be submitted for review and approval. Should a phased-in occupancy be required, a phased-in occupancy plan, to include a separation between occupied and unoccupied areas, emergency egress, and building fire protection must be filed along with the design plan revision.
All plans and documents shall meet the requirements set forth in the Building Development DivisionCustomer ePlans Guide and be submitted online in ePortal, according to a county press release.
In 2020, insatiable demand for Data Centers surged with the construction pipeline reaching near record-levels, according to Jones Lang LaSalle (JLL). Given the expected exponential growth in information communications technology and commensurate data storage infrastructure needs, the Prince William Board of County Supervisors approved the amended zoning ordinance for the Data Center Opportunity Zone (DCOZ) Overlay District, in June 2019.
“We are pro-business and continuously taking steps forward to provide a framework in which all businesses can grow and move expediently through necessary regulatory processes, as evidenced in the recent advances in ePortal and new online and automated services,” said Wade A. Hugh, Director Department of Development Services. “Data Centers are unique structures and require a high level of expertise throughout the entire building construction phase and these new policy and procedures help guide the process.”
All forms for the Data Center New Structures Policy, such as the application request form, checklist, and footing and foundation checklist are located in the Building Development Forms Management System, which provides easy access to all forms related to the building development process and the Virginia Uniform Statewide Building Code (VUSBC).
For more information on ePlan submissions please find the ePlan How-To Guide video, contact Plan Intake at (703) 792-4040 or [email protected]. For assistance with ePortal please contact (703) 792-6875 or [email protected].