Residents should expect to see increased lane closures in the coming months at the intersection of Route 1, Route 17 Business and Route 218 in Stafford’s Falmouth district.
The closures are a part of the $22.1 million dollar construction project being completed by the Virginia Department of Transportation (VDOT), according to a VDOT release.
Construction on the intersection began back in March 2014 as part of an improvement project. Tavares Concrete, Inc is completing the project.
Currently, construction on the project is at 50% completion. The project includes building new turn lanes and travel lanes, as well as sidewalks, which will be open for use in September 2015, said a VDOT release.
According to a VDOT release, the purpose of the project is to unclog the intersection, as it is an important alternate route for Interstate 95, and local passage between Stafford County and the City of Fredericksburg.
“We appreciate the cooperation and patience of drivers over the past year during the demolition, utility relocation, and early construction work. We look forward to wrapping up construction over the next six months to deliver this project in September,” said Michael Coffey, P.E., VDOT’s Assistant District Administrator for Construction, Fredericksburg District in a release.
Residents should expect single lane closures near the intersection most evenings, Sunday through Thursday. VDOT stated that they will avoid lane closures during peak traffic times including rush hour on weekdays, Friday nights, and weekend days.